  • Anonymous

    Does anyone know the rules about changing planned end dates? We have a few learners that originally signed up to do an Award which finished on 31/07/12. However they are staying on to do a Certificate which will finish in Dec 12. I know the SFA don’t like us changing planned end dates but it would seem mad to set up a new course using the old A51a field (whatever it is now). Does anyone know if exceptions are made in this scenario?

     
    #198

    Martin West
    Participant

    Hi Chris,
    The planned end date must not be changed, the only exception is to correct an error.
    In your scenario you will need to create a certificate aim as the award has already ended.

     