    Hi,
    We had some learners transfer to us after they had undertaken part of their learning with another provider that has ceased trading. An admin error has been made and the learner have been put on the ILR for a full duration of the program and not adjusted the time. Can I adjust the PED so that we can get the learners to gateway/EPA when they are ready which is around 6 months before what the PED states on ILR.

    Are there any options does anyone know ?

    Thanks in Advance

     
    #327783

    Spats
    Participant

    You can change a planned end date if it’s legitimately due to something like an error of data entry.

     
    #327787

    CLH75
    Participant

    Even if its after the 42 day qualifying period ? I did read in the rules you can change if its an admin error like you say but I was worried about making the change after the 42 days or does this not matter when its an admin error ?

     
    #327796

    Spats
    Participant

    You should still be fine. The PSM explicitly says that the only time you can change start and end dates after the 42 days is if you identify an error.

     
    #327803

    CLH75
    Participant

    Brilliant Thanks Spats

     
    #327805

    Spats
    Participant

    Here you go:

    5.3.2 Changes to the Learning start and end dates
    389. These fields inform the funding received. You must not make any changes to the
    start or planned end dates after the funding qualifying period, except to correct
    errors.