  • Lisa
    Participant

    Hi

    Can anyone explain, simply, where stats sit if an apprenticeship learner who was due to achieve this contract year (i.e. before 31.07.2017) but does not achieve until September 2017 – so in next contract year.

    Many thanks!

     
    #179142

    Steve Bowler
    Participant

    Hi Lisa,

    For the ‘Overall’ QAR the learner would fall into 17/18 as their Hybrid End Year is 17/18 (later of Target Date or Actual End Date).

    For the ‘Timely’ QAR the learner would fall into 16/7 as their Target Date is in 16/17.

    Hope that helps 🙂

    Steve

     
    #179156

    Lisa
    Participant

    Hi Steve

    Thank you – I did think so – you have clarified is perfectly for me.

     
    #179161